Phase 3 (completed 2021)

This phase re-piped all the Phase 3 flats and replaced pipework for the riser cupboard in the communal corridor. Heating, hot water and cold feed supplies were replaced.
The work involved removing the existing supplies within each riser cupboard before installing the new pipes. To do so, the water supply had to be cut off temporarily.
Work progressed on one riser at a time. So a maximum of 6 properties were affected at any one time.
Phase 2 (completed 2020)
This phase of works changed from our original plan, because of the Covid restrictions. We were originally due to start work to re-pipe riser cupboards and flats. Instead, we focused on the communal areas in each of the remaining phases, so we could continue to progress the project.
Phase 1 (completed 2019)
The first phase mainly affected the tunnels under the ground-floor communal corridors. We installed new supply pipes to and from the communal plant rooms, ready for connection in future phases.